Temporary Roadway Formation

Scope of Works

  • Setting up temporary fencing around site
  • Installation of height restriction barrier
  • Excavation & leveling of soil
  • Installation & rolling of stone

Works were carried out in order for Electricity North West to bring a crane on site for maintenance work on the substation pylons.

Project Details

Recent Works

Project Gallery

Corner

Scope of Works:

  • Setting up temporary fencing around site
  • Installation of height restriction posts
  • Excavation of soil/other material
  • Stone laid and rolled to create stable road

Work carried out to enable a crane to be placed on site in order for Electricity North West to make changes to the pylons at the substation.